Update for the house on the 9th week.
1. Roofs up
2. Plasterboard finish
3. Kitchen module/cupboards setup.
4. Internal / External doors installed
5. Cornice / wall skirting done.
6. basin/ bath tub were placed.
Most of the internal works were done during the last 4 weeks as we had a delay waiting for the bricks. Reason being is that the machine that manufacture the bricks is down so we have to wait till the 28th of this month.
Here are some of the photos.
Kitchen benchtop and cupboard

Main door installed but not yet painted

Common bathroom basin and bathtub. Bathroom tiles not yet layed

Family lounge. Bi-fold door to the outdoor room were placed.

House facade

It’s getting a bit exciting now that we can see the looks of the house inside and out. But we are definitely looking forward to see how it looks with the bricks. Normally the bricks should be layed a month ago if not for the delay. Never the less its still good because interior works is still on going. They call it reverse construction were they continue to work the interior while waiting for the bricks.
Related Articles
- December 10, 2009 -- Things to know during the walk through
- September 6, 2009 -- roof frames up
- November 18, 2009 -- Final stage of house construction
- November 10, 2009 -- 13th Week Metricon House Building
- September 3, 2009 -- Wall frames are up
Parse error: syntax error, unexpected $end in /home/content/e/r/w/erwinreyes31/html/wp-content/themes/savvy/comments.php on line 124