Tuesday, November 10 2009    •    File Under: house constructionproperties

There are several noticeable improvements now that were on the 13th week of house construction. Focusing first on the internal portion of the house, the list are as follows:

1. Wall and Floor tiles were laid.
082
078

2. Electrical items were installled such as power points, downlights, switches, kitchen and dining lights.

3. Internal paintings were finished.

4. Ducted heating points (10 of them) were placed as well as smoke alarm.

5. Toilet and laundry basins were installed as well as fittings. The plumber is kind enough to let me in the house though we are already in lock up stage.
062

External portions:

1. Bricks are 90% completed. The bricks should have been long time finish at this stage however, there has been 2 months delay on the supplier.

2. External doors were fitted.

3. Aerial Antenna were installed.

4. External weather proof powerpoints were installed, portico lights etc…

Base on mymetricon status display, the house is more than 80% completed. The building process is considerably smooth. Were are satisfied with the process.

Related Articles

Tags: , ,

del.icio.us:13th Week Metricon House Building digg:13th Week Metricon House Building spurl:13th Week Metricon House Building wists:13th Week Metricon House Building simpy:13th Week Metricon House Building newsvine:13th Week Metricon House Building blinklist:13th Week Metricon House Building furl:13th Week Metricon House Building reddit:13th Week Metricon House Building fark:13th Week Metricon House Building blogmarks:13th Week Metricon House Building Y!:13th Week Metricon House Building smarking:13th Week Metricon House Building magnolia:13th Week Metricon House Building segnalo:13th Week Metricon House Building gifttagging:13th Week Metricon House Building

Parse error: syntax error, unexpected $end in /home/content/e/r/w/erwinreyes31/html/wp-content/themes/savvy/comments.php on line 124